Preparation: Put the safety signs in place, put the slotting machine and the joint filling machine in place; prepare slotting according to the construction requirements, start the joint filling machine to preheat, add crack sealant and stir, control the temperature between 170℃ and 200℃.
Grooving: Install a suitable saw blade according to the size required by the construction (recommended width and depth are both 13cm-26cm), adjust the required depth, and perform slotting operations.
Clean up: After manual cleaning, use an air compressor or a knapsack blower to thoroughly clean up the debris and dust in the seam.
Filling joints: When the crack sealant temperature is between 170℃ and 200℃, start to fill the joints; the temperature of the joints is recommended to be above 10℃; if the temperature in winter is below 5℃, it is best to preheat the part of the groove before starting to fill the joints.
Maintenance: After 15 minutes of filling, the traffic can be opened.